Restaurant pre-opening checklist (India) — T-90 to Day +7

80+ tasks sequenced across 8 phases — concept lock at T-90, build & utilities at T-60, equipment install at T-30, hiring & statutory at T-14, trial & training at T-7, final readiness at T-1, opening on Day 0, first retro on Day +7. Filter the list to your restaurant format (QSR / casual dining / cloud kitchen / bar / fine dining), pick a target launch date, and the page renders an absolute due-date next to every phase. State persists in your browser, you can print the full list as an A4 wall chart, or export the phase milestones as an .ics file your project manager can drop into any calendar app. No signup.

Configure your plan

0%
0 / 79 done· Casual dining · launch 10 Aug 2026
Saved locally in this browser. Switch format or date to start a new plan; the previous one stays under its own key.
  • Legal
    Freeze restaurant concept + format (QSR / casual / cloud / bar / fine dining)
    Why this matters

    Format drives every downstream decision: kitchen layout, licences, POS scope, staff count, aggregator strategy. Changing it after T-60 means redoing utility load, equipment POs, and hiring plan.

  • Legal
    Sign registered rent / lease agreement, get landlord NOC
    Why this matters

    Every other licence application asks for the rent agreement + landlord NOC as proof of premises. Unsigned lease = no FSSAI, no Trade Licence, no GST registration possible.

  • Legal
    File FSSAI Central / State licence application on FoSCoS
    Why this matters

    FSSAI takes 30–60 days to issue. Operating without it on Day 0 attracts penalty up to ₹5 lakh under Sec 63 of FSS Act. Central licence required if turnover > ₹20cr or multi-state ops.

  • Legal
    Apply for GST registration (Form REG-01)
    Why this matters

    You need a GSTIN to issue a tax invoice on Day 1, to onboard with Swiggy/Zomato, and to claim ITC on equipment purchases. Allow 7–15 working days.

  • Legal
    Apply for Shop & Establishment registration (state portal)
    Why this matters

    Mandatory under state S&E Act for any commercial premises with employees. Required to open a current account, register with EPFO/ESIC, and renew annually.

  • Legal
    Apply for Trade Licence from local municipal body
    Why this matters

    Local municipal corporation (BBMP / BMC / MCD etc.) issues this. Without it, your premises is technically operating illegally and the corporation can seal it.

  • LegalBar, Fine dining, Casual dining only
    Apply for liquor licence (CL-9 / FL-III / state equivalent)
    Why this matters

    Liquor licences take 3–6 months in most states and have public-objection windows. If the bar P&L depends on liquor margin, missing this on Day 0 wipes 30–40% of revenue.

  • Menu & Supply
    Lock initial menu (item count, recipe outline, target food-cost %)
    Why this matters

    Equipment list, kitchen layout, supplier search, and POS configuration all hang off the menu. A frozen menu at T-90 prevents the classic "we added a tandoor in week 6" cascade that delays opening by 3 weeks.

  • Kitchen & Equipment
    Finalise equipment list with capex and lead times
    Why this matters

    Imported items (combi ovens, espresso machines, cold rooms) have 8–12 week lead times. Locking the list at T-90 means POs can be raised at T-60 and equipment lands at T-30.

  • Finance
    Run breakeven analysis using Breakeven (covers/day to hit profit)
    Why this matters

    Investor reality check before any capex hits. If breakeven covers/day exceeds 1.5x your seating turnover capacity, the unit economics are broken before you open the doors.

  • Finance
    Confirm capex + 6 months working capital in bank
    Why this matters

    Indian restaurants take 6–9 months to hit positive cash flow. Opening with < 6 months runway is the #1 reason first-time owners shut down within Year 1.

  • Finance
    Open current account in restaurant entity name
    Why this matters

    Need a separate business account before vendor POs, GST registration, and payment gateway onboarding. Personal account fund-flow muddies the books and triggers IT scrutiny.

  • Site & BuildCasual dining, Bar, Fine dining only
    Engage architect / kitchen designer with signed scope
    Why this matters

    Kitchen designers control the most expensive sq-ft in the restaurant. Engaging them late means civil work has to be redone at T-60 to fit the equipment grid.

  • Site & Build
    Sign off kitchen civil + plumbing + drainage layout drawings
    Why this matters

    Once the slab is poured, plumbing changes cost 10x. Final drawings must include grease trap location, water supply points, drainage slope, and equipment power outlets.

  • Site & Build
    Apply for electrical load sanction (DG backup sized to load)
    Why this matters

    A 60-cover casual dining typically needs 50–80 kW. Sanction takes 30–45 days. Opening on a residential connection trips on the first lunch service.

  • Site & Build
    Apply for commercial water connection + storage tank sizing
    Why this matters

    Restaurants consume 800–1500 litres/cover/month. Without a sanctioned commercial line you depend on tankers, which means a single dry day shuts service.

  • Site & BuildCasual dining, Bar, Fine dining, QSR only
    Apply for piped gas (PNG) connection or LPG manifold approval
    Why this matters

    PNG requires Gas Distribution Co. survey + safety NOC, lead time 45–60 days. LPG manifold needs PESO approval + fire NOC.

  • LegalCasual dining, Bar, Fine dining only
    Apply for Fire NOC (state Fire Service)
    Why this matters

    Fire NOC is mandatory for any premises with assembly area > 100 sqm in most states. Inspection takes 30 days; rectifications add another 15. Operating without it = sealing risk.

  • LegalCasual dining, Bar, Fine dining only
    Apply for State Pollution Control Board consent (CTE / CTO)
    Why this matters

    Restaurants with seating > 36 covers or DG > 5 kVA fall under SPCB consent. Mandatory for FSSAI Central licence and operating multi-cuisine kitchens.

  • Kitchen & Equipment
    Raise purchase orders for kitchen equipment (40% advance)
    Why this matters

    Indian equipment vendors need 40–50% advance for fabricated items (hood, exhaust, work tables). Imported items lock 30% on PO + 70% before BL release.

  • Menu & Supply
    Sign FMCG supplier agreements (oil, atta, dal, masala, dairy)
    Why this matters

    FMCG distributors offer 7–15 day credit only after 2–3 months of consistent purchase history. Locking suppliers at T-60 means credit lines are open by T-7.

  • Menu & Supply
    Identify mandi vegetable + fruits supplier (or app like Otipy / WayCool)
    Why this matters

    Vegetables are 18–22% of food cost and the highest-variance line. Mandi sourcing needs a runner; app sourcing needs a cut-off time discipline.

  • Menu & Supply
    Lock meat / chicken / fish / paneer supplier with weekly QC protocol
    Why this matters

    Protein is your biggest food-safety risk. Supplier should provide FSSAI licence copy, daily temperature log, and accept rejects without dispute.

  • Menu & SupplyQSR, Casual dining, Cloud kitchen only
    Order branded delivery packaging (12-week lead time for printed)
    Why this matters

    Aggregator launch demands branded packaging from Day 1 for organic photo CTR. Printed packaging requires 5,000-unit MOQ and a 10-week press cycle.

  • Marketing
    Start Swiggy / Zomato onboarding (FSSAI + GST + bank docs)
    Why this matters

    Aggregator onboarding takes 4–6 weeks. Submitting at T-60 means you go live within 7 days of opening, which protects Day 7 revenue.

  • Legal
    Bind fire + public liability + workmen comp insurance
    Why this matters

    A single kitchen fire wipes 6 months of capex. WC is statutory if you have 10+ workmen. Buy at T-60 so cover starts before equipment lands at T-30.

  • Kitchen & Equipment
    Begin equipment installation (cooking line first, then refrigeration)
    Why this matters

    Cooking line first → vendor commissioning → refrigeration last. Refrigeration commissioning needs ambient temperature stable, which is impossible during civil dust.

  • Kitchen & EquipmentCasual dining, Bar, Fine dining, QSR only
    Install hood, exhaust, and ESP / scrubber for emissions
    Why this matters

    SPCB and resident-association complaints kill more restaurants than competition. ESP / scrubber installed on Day 1 prevents kitchen smoke escalation in week 4.

  • Kitchen & Equipment
    Commission walk-in / under-counter chillers + temperature loggers
    Why this matters

    FSSAI inspection asks for daily temperature logs from Day 1. Install loggers (digital, downloadable) before opening, not after the first audit notice.

  • Tech & POS
    Procure POS hardware (terminal, KOT printers, cash drawer, BHIM QR)
    Why this matters

    KOT printer placement (1 per kitchen station) determines kitchen workflow. Procuring late means you wire the terminal in the wrong spot and rip cables in week 2.

  • Tech & POS
    Sign POS contract (Petpooja / UrbanPiper / Posist) + map menu
    Why this matters

    POS menu mapping (modifiers, taxes, channel pricing) takes 2 weeks. Doing it at T-30 means Day 1 menu is bug-free and aggregator inventory is in sync.

  • Tech & POS
    Set up payment gateway (Razorpay / PhonePe) + UPI QR + card EDC
    Why this matters

    EDC machines from banks take 15 working days. UPI QR + Razorpay can go live in 48 hours but bank EDC has the lowest MDR for cards above ₹2,000.

  • Tech & POS
    Configure tax invoice template (GSTIN, HSN/SAC, place of supply)
    Why this matters

    Restaurant invoice MUST show GSTIN, HSN 9963, "Restaurant service @ 5% (no ITC)" or 18% (with ITC if AC + bar combined). Wrong format = customer complaint + GST notice.

  • Menu & Supply
    Build menu engineering matrix (star / plowhorse / puzzle / dog)
    Why this matters

    Menu mix on Day 30 will not match the menu mix on Day 1 — but knowing target contribution margin per item lets you re-price intelligently after the first 100 covers.

  • Menu & Supply
    Document standard recipe cards (yields, costs, plating, photos)
    Why this matters

    Recipe cards are the only thing that survives chef turnover. Without them, food cost drifts up 4–5% within 3 months as portions creep.

  • MarketingQSR, Casual dining, Cloud kitchen only
    Schedule Swiggy / Zomato food photoshoot
    Why this matters

    Aggregator menu photos drive 60% of conversion. Their in-house shoot books out 3 weeks ahead and has format constraints (square, white background, hero plating).

  • Hiring & Training
    Close all hires (chef, cooks, helpers, captains, manager, cashier)
    Why this matters

    Hiring at T-7 means staff arrive without uniforms, without PF/ESI registered, without basic SOP exposure. They learn on customer time = bad first reviews.

  • Legal
    Prepare statutory registers (muster, wages, leave, overtime)
    Why this matters

    Labour inspection in week 2 will ask for these. Use /tools/attendance-register for the muster format. Maintained from Day 1, not retrofitted.

  • Legal
    Lock salary slip format (use Salary slip generator)
    Why this matters

    Salary slip with EPF + ESI + PT breakup is mandatory under Payment of Wages Act. Operators who hand out cash without slips get caught in the first inspection.

  • Legal
    Register establishment with EPFO + ESIC (if 10+ / 20+ staff)
    Why this matters

    EPF mandatory at 20+ employees, ESI at 10+ in notified areas. Registration takes 7–10 days. Late registration = backdated contributions + 12% interest.

  • Menu & Supply
    Confirm supplier credit lines (7-day, 15-day, cash terms)
    Why this matters

    Day 1 inventory needs to land on credit, not cash, or working capital evaporates in week 1. Suppliers honour T-60 negotiations only if you confirm credit at T-14.

  • Finance
    Decide opening cash float (default ₹5,000 per till)
    Why this matters

    Cash float should be enough to give change for the first 30 covers without breaking large notes. Use /tools/cash-variance from Day 1 to track close-out variance.

  • Hiring & Training
    Order uniforms + non-slip footwear + chef coats + name badges
    Why this matters

    Uniform consistency on Day 1 is a CTR signal in customer photos. Chef coats and non-slip footwear are also a workplace safety + WC insurance requirement.

  • Site & Build
    Sign pest control + housekeeping contracts
    Why this matters

    FSSAI mandates documented pest control by a licensed agency with monthly visit log. Reactive pest treatment after a customer complaint costs the restaurant a 1-star Zomato review.

  • Soft Launch
    Run 3 trial-cooking rounds (full menu, batch sizes, plating)
    Why this matters

    Trial cooking exposes equipment hot-spots, recipe yield drift, plating bottlenecks. Always do 3 rounds: solo chef, full team, full team + timed service.

  • Hiring & Training
    Document opening / closing / cleaning SOPs (1-page each, laminated)
    Why this matters

    SOPs taped at the workstation outperform 50-page manuals. Opening SOP, closing SOP, daily-cleaning checklist, weekly-deep-cleaning checklist — that is enough for Year 1.

  • Hiring & Training
    Run 3 days of staff training (POS, plating, service script, complaint handling)
    Why this matters

    POS muscle memory takes 3 days. Without it, captains punch wrong KOTs on Day 1, kitchen fires the wrong dish, and the customer leaves a "slow service" review.

  • Tech & POS
    Load complete menu into POS + aggregator with photos and modifiers
    Why this matters

    Menu-on-paper to menu-on-POS conversion always reveals 10–15% missing modifiers (extra cheese, spicy, jain). Catch this at T-7, not on Day 1.

  • Tech & POS
    End-to-end KOT + bill printer test (every station, every channel)
    Why this matters

    Printer failure on Day 1 lunch = manual KOT slips = kitchen errors compound. Test from POS terminal → kitchen printer → bill printer with 20 dummy orders.

  • MarketingQSR, Casual dining, Cloud kitchen only
    Schedule aggregator go-live for Day +3 (not Day 0)
    Why this matters

    Day 0 dine-in surge + aggregator orders = kitchen melt. Bring aggregator live on Day +3 once dine-in flow is calibrated.

  • Marketing
    Seed Instagram + Google Business Profile (location pin, photos, hours)
    Why this matters

    Google Business Profile takes 3–5 days to verify. Without verification on Day 1, "near me" search doesn't surface you. Verified profile = 4x walk-in discoverability.

  • Marketing
    Conduct food + interior photoshoot for menu + social + aggregator
    Why this matters

    Hero photos drive 60% of aggregator CTR and 80% of Instagram engagement. Schedule the shoot during a trial cooking round so plating is consistent with what guests will see.

  • Site & BuildCasual dining, Bar, Fine dining only
    Test AC, music, lighting at full load (60% capacity dummy)
    Why this matters

    AC trips, speaker hum, glare on customer-side seats — all show up at full load. Test before reviews start showing up.

  • Marketing
    Lock soft-launch invite list (50–80 friends, family, hyperlocal influencers)
    Why this matters

    Soft launch is for kitchen pacing, not PR. Invite people who will give honest feedback and forgive mistakes. NOT food bloggers — they come on Day +14.

  • Soft Launch
    Schedule 1 mystery diner round during T-1 evening service
    Why this matters

    A trained mystery diner catches service gaps that staff and friends miss — wait time, order accuracy, billing accuracy, tip handling, washroom cleanliness.

  • Legal
    Compile physical + digital licence folder (FSSAI, Trade, S&E, Fire, Liquor, GST)
    Why this matters

    Inspectors and excise officers ask to see the licence folder, not your phone. Laminated copies displayed at billing counter signal "this place runs tight".

  • Site & Build
    Service + tag fire extinguishers (CO2 in kitchen, ABC in dining)
    Why this matters

    Fire NOC and fire-safety drills require extinguishers tagged with last-service date. Untagged extinguishers fail inspection and can void insurance after a fire.

  • Site & Build
    Stock first-aid box (burn cream, antiseptic, bandages, eye wash)
    Why this matters

    Kitchen burns and cuts happen. First-aid box is mandatory under Factories Act / S&E Act. WC insurance claims require documented first-aid administration.

  • Legal
    Add EPF / ESI / GSTR-1 / GSTR-3B / TDS dates to Compliance cal
    Why this matters

    First missed return is the most expensive — late fees compound and ITC blocks downstream. Subscribe the .ics into the manager + accountant calendars before opening.

  • Hiring & Training
    Final uniform + grooming + nametag check across all staff
    Why this matters

    First-day photos circulate on guest social media within hours. Mismatched uniforms or missing name tags read as "amateur" in those photos.

  • Finance
    Count and sign opening cash float (₹5,000) into till
    Why this matters

    Cash float counted + signed in writing by manager + cashier creates the audit trail Day 0 close-out variance computes against.

  • Hiring & Training
    Serve full staff meal + briefing the evening before opening
    Why this matters

    Staff meal = recipe + service rehearsal + team rapport + the chef gets a final tasting of the actual day-1 plating. Costs ₹300 per head, returns 10x in service quality.

  • Finance
    Record opening cash float (₹5,000) in DSR + log book
    Why this matters

    Without a recorded float, every cash variance computation is meaningless. Use /tools/daily-sales-report to capture float + denomination breakup.

  • Finance
    Print DSR template + petty cash voucher pad for Day 1
    Why this matters

    Use /tools/daily-sales-report and /tools/petty-cash-voucher to print the templates. Manager fills DSR at end of shift; cashier issues petty cash vouchers for any sub-₹500 purchase.

  • MarketingQSR, Casual dining, Cloud kitchen only
    Decide aggregator switch-on time (recommend Day +3)
    Why this matters

    Premature aggregator-on = kitchen overload + bad reviews from delayed orders. Many successful operators stay aggregator-off for the first 72 hours.

  • Hiring & Training
    Manager briefing 90 min before service: covers expected, station assignments, escalation tree
    Why this matters

    Day 0 has the highest probability of complaints. Pre-briefing stations and giving the manager an explicit complaint-escalation tree prevents an unhappy guest from becoming a 1-star review.

  • Soft Launch
    Open doors at advertised time (not late)
    Why this matters

    A late opening on Day 0 is the customer's first signal about your discipline. Open on time even if 1 station is still settling — recover the station, not the timing.

  • Marketing
    Place feedback cards / QR-to-Google-review on every table
    Why this matters

    Day 0–14 is the only window when guests are excited enough to leave a 5-star review unprompted. After that you have to ask.

  • Tech & POS
    Settle first 5 bills end-to-end (KOT → cook → fire → bill → payment) and audit
    Why this matters

    First 5 bills expose every POS misconfiguration: tax rate, modifier price, payment gateway sync, KOT print delay. Audit them before bill #20.

  • Finance
    Run formal Day 0 cash close-out + DSR + variance log
    Why this matters

    Day 0 cash close sets the discipline. Use /tools/cash-variance for the close-out math. Note variance reasons in writing — these are tomorrow's training points.

  • Finance
    Review 7-day cash variance trend + reasons
    Why this matters

    A pattern emerges by Day 7: persistent over-shorts mean dropped covers, persistent over-rings mean cashier nicking. Decide on counter-measures before the leak hits ₹50k/month.

  • FinanceQSR, Casual dining, Cloud kitchen only
    Reconcile Swiggy / Zomato settlements vs POS sales
    Why this matters

    Aggregator settlements lag by 7–10 days and net-of-commission, taxes, insurance, late-cancel deductions. Reconciling early establishes the dispute-window discipline.

  • Finance
    Confirm payroll cycle (weekly / fortnightly / monthly + cut-off date)
    Why this matters

    Restaurant staff often need weekly or fortnightly cycles. Lock cycle, cut-off, advance policy in writing — verbal commitments cause attrition in week 4.

  • Finance
    Take first food-cost % reading using Food cost (period mode)
    Why this matters

    Day 7 food-cost is always 4–6% above target due to opening waste, recipe drift, supplier teething. A first reading establishes the baseline you measure improvements against.

  • Hiring & Training
    Run team retro (what worked, what broke, what to fix in week 2)
    Why this matters

    Frontline staff catch service gaps owners never see. A 30-min retro in week 1 captures the biggest wins; without it those issues become normalised by week 4.

  • Marketing
    Sweep Google + Zomato + Swiggy reviews; reply to every one
    Why this matters

    Replying to reviews in week 1 trains the algorithm and the customer base that you read feedback. It changes the review tone within 30 days.

  • Legal
    Prepare data for first GSTR-1 / GSTR-3B (whichever lands first)
    Why this matters

    First GST return shapes how the accountant maps your POS data. Get this right and monthly compliance becomes a 30-min job; get it wrong and the next 6 months are reconciliation hell.

  • Menu & Supply
    Give suppliers structured Week-1 feedback (quality, timing, pricing)
    Why this matters

    Suppliers calibrate to clients in the first month. Structured feedback now (preferred SKUs, reject criteria, delivery window) sets the relationship for the year.

  • Legal
    Verify FSSAI licence + GST display board are mounted at billing counter
    Why this matters

    FSSAI licence display is mandatory at the entrance. GST registration certificate display is mandatory at the principal place of business. Most opening checklists miss this until the first inspection.

How this is sequenced

Most first-time owners try to do everything in parallel and then discover at T-30 that the kitchen civil work cannot start because the equipment list isn't locked, that the equipment list cannot be locked because the menu isn't frozen, and that the menu can't be frozen because the concept is still drifting between "casual dining" and "modern bar". The result is a domino — every task in every downstream phase slips, and the opening date moves by 6 weeks. The T-90 / T-60 / T-30 sequencing here is built backwards from the launch date with the dependency chain made explicit: concept locks the menu, menu locks the equipment list, equipment list locks the POs, POs lock the install window, install locks the trial cooking, trial cooking locks the soft launch, soft launch locks Day 0.

The other thing the sequencing fixes is the licence pipeline. FSSAI takes 30–60 days, GST takes 7–15 days, fire NOC takes 30–45, a liquor licence takes 90–180. Operators who file these at T-30 discover at T-7 that they don't actually have a fire NOC and end up opening with a sealed kitchen risk hanging over them. Filing at T-90 (or T-60 for fire NOC) means every licence is in hand before the soft launch, and the licence folder at the billing counter is complete on Day 0 instead of Day +45.